Larry Summers asks why the Anderson Bridge in Boston is taking so long to rebuild.
How, we ask, could our society have regressed to the point where a bridge that could be built in less than a year one century ago takes five times as long to repair today? Here are some of the reasons that have contributed to the delay:Made me think of Irving Kristol's comments about being mugged by reality.
In order to adhere to strict historical requirements overseen by the Massachusetts Historical Commission, the Massachusetts Department of Transportation had to order special bricks, cast by a company in Maine, to meet special size and appearance specifications from the bridge’s inception in 1912.
At the same time, extensive permitting and redesigns haven’t helped. For instance, once construction had already started on the bridge, the contractor, Barletta Heavy Division, discovered that an existing water main would need to be relocated. With the subsequent change order and additional Massachusetts Water Resources Authority permitting processes, an additional 357 days were tacked on to the original contract completion date.
To cap it off, after resisting for years the inclusion of pedestrian underpasses in bridge rehabilitation, MassDOT changed course in 2014 and agreed to revise the design so as not to preclude the construction of an underpass in the future. The contractor then had to move a major utility pipe so that an underpass could fit underneath; meanwhile, another 256 days of delay were added to the project. The entire project is now 22 months behind schedule.
Bill
No comments:
Post a Comment